Flood Control and Drainage17CF0058

FLOOD CONTROL STRUCTURES/FACILITIES, CONSTRUCTION/MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURE AND DRAINAGE SYSTEM REHABILITATION/IMPROVEMENT OF CABU RIVER FLOOD CONTROL STA. 6+ 901.40-STA. 7+256.40, BRGY. CABU CABANATUAN CITY, NUEVA ECIJA

FLOOD CONTROL STRUCTURES/FACILITIES, CONSTRUCTION/MAINTENANCE OF FLOOD CONTROL MITIGATION STRUCTURE AND DRAINAGE SYSTEM REHABILITATION/IMPROVEMENT OF CABU RIVER FLOOD CONTROL STA. 6+ 901.40-STA. 7+256.40, BRGY. CABU CABANATUAN CITY, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱47,162,502.98. Status: Reported complete (DPWH). Contractor on record: R A PAHATI CONST. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Maintenance of Flood Control Mitigation Structure and Drainage System/Rehabilitation/Improvement of Cabu River Flood Control Sta. 6+901.40 - Sta. 7+333.80 (432.40 l.m), Brgy. Cabu, Cabanatuan City, Nueva Ecija
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0015657

₱32,557.00 · FY2017

Released to Tagakpan National Mo High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,162,502.98

Progress

Reported complete (DPWH)

Start Date

July 10, 2017

Target End

December 19, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.