Flood Control and Drainage19CG0015

CONSTRUCTION/ REHABILITATION OF MESALIPIT CREEK, BACOLOR, PAMPANGA (R.A. 9506- BACOLOR REHABILITATION ACT)

CONSTRUCTION/ REHABILITATION OF MESALIPIT CREEK, BACOLOR, PAMPANGA (R.A. 9506- BACOLOR REHABILITATION ACT) is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱18,521,968.05. Status: Reported complete (DPWH). Contractor on record: STARDON CONST AND TRADING. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-19-0008831

₱269,451.00 · FY2019

Released to Veterans General Hospital (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

29 projects · ₱157.3M total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAR REGIONAL OFFICE BUILDING), CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2023₱13.9M
Reported complete (DPWH)
No sat.

CONCRETING OF CONCEPCION-DOLORES-MALIWALU ROAD, BACOLOR, PAMPANGA (RA 9506 BACOLOR REHABILITATION ACT)

Pampanga 1st DEO, Region III

2017₱13.9M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF ROADS INCLUDING DRAINAGE SYSTEMS, DEL ROSARIO AND SAN JUAN, CIT

Pampanga 1st DEO, Region III

2023₱11.1M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF MAGLIMAN ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2023₱10.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SAN ROQUE, MDRRMO, ANGAT, BULACAN

Bulacan 2nd DEO, Region III

2023₱9.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, ACLI ES, MEXICO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱6.6M
Reported complete (100% progress, DPWH status On-Going)
View all 29 projects →

4. Implementation

Contract Amount

₱18,521,968.05

Progress

Reported complete (DPWH)

Start Date

June 5, 2019

Target End

September 22, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.