GAA 2025 OO-125BD0011

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO CITY-ENRILE DIVERSION ROAD, CAGAYAN

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - TUGUEGARAO CITY-ENRILE DIVERSION ROAD, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱38,499,558.45. Status: Past target date (DPWH On-Going). Contractor on record: MEGAY CONST INC FORMERLY: MEGAY CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Paranan River, Baggao, Cagayan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-25-0013374

₱776,534.00 · FY2025

Released to Emigdio A. Bondoc High School, San Luis (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

130 projects · ₱5.6B total · 2 flags

Other projects by this contractor

No sat.

REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CAGAYAN RIVER FLOOD MANAGEMENT PROJECTS, BRGY. ANQUIRAY, AMULUNG, CAGAYAN (DOWNSTREAM) STA. 0+320 - STA. 0+520

Cagayan 3rd DEO, Region II

2024₱136.4M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF FLOOD CONTROL MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CAGAYAN RIVER FLOOD MANAGEMENT PROJECTS, BRGY. PATA, ENRILE, CAGAYAN (DOWNSTREAM) STA. 0+230 - STA. 0+430

Cagayan 3rd DEO, Region II

2024₱136.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - PEÑABLANCA- CALLAO CAVE RD - K0482+600 - K0482+692

Cagayan 3rd DEO, Region II

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - PEÑABLANCA - CALLAO CAVE RD. - PHASE III PACKAGE 5

Cagayan 3rd DEO, Region II

2023₱96.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - PEÑABLANCA - CALLAO CAVE RD. - PHASE III PACKAGE 4

Cagayan 3rd DEO, Region II

2023₱96.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - PEÑABLANCA - CALLAO CAVE RD. - PHASE III PACKAGE 2

Cagayan 3rd DEO, Region II

2023₱96.4M
Reported complete (DPWH)
View all 130 projects →

4. Implementation

Contract Amount

₱38,499,558.45

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

October 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.