Construction of Dike23FB0148

Construction of Flood Mitigation Structure (Revetment Wall), Sitio Misua B, Banquerohan, Legazpi City, Albay

Construction of Flood Mitigation Structure (Revetment Wall), Sitio Misua B, Banquerohan, Legazpi City, Albay is a DPWH-tracked public work in LEGAZPI CITY (CAPITAL) (ALBAY), ALBAY, Region V. Reported contract value: ₱48,885,924.75. Status: Reported complete (DPWH). Contractor on record: CENTERWAYS CONST AND DEVELOPMENT INC / CBC CONST & SUPPLY. Figures trace to sumbong.

LEGAZPI CITY (CAPITAL) (ALBAY), ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure (Revetment Wall), Sitio Misua B, Banquerohan, Legazpi City, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0021169

₱646,190.00 · FY2023

Released to Bagamanoc Rural Development High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱48.9M total · 0 flags

4. Implementation

Contract Amount

₱48,885,924.75

Progress

Reported complete (DPWH)

Start Date

June 19, 2023

Target End

November 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.