GAA 2016 MFO-216CG0028

REPAIR/REHABILITATION OF ROAD DIKE AND SLOPE PROTECTION OF PASIG POTRERO RIVER AT BACOLOR, PAMPANGA

REPAIR/REHABILITATION OF ROAD DIKE AND SLOPE PROTECTION OF PASIG POTRERO RIVER AT BACOLOR, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱45,742,628.40. Status: Reported complete (DPWH). Contractor on record: FERDSTAR BUILDERS INC. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Projects in Central Luzon - Rehabilitation of Slope Protection along Pampanga River, San Luis, Pampanga
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-16-0014620

₱695,753.00 · FY2016

Released to Desiderio C. Gange (Maabay) National High Scho For (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

139 projects · ₱8.9B total · 1 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS-CONSTRUCTION OF RING DIKE WITH PUMPING STATION (PHASE 2 & 4), MACABEBE-MASANTOL, PROVINCE OF PAMPANGA

Region III, Region III

2024₱354.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION), PACKAGE 3, PROVINCE OF PAMPANGA

Region III, Region III

2020₱193.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ABACAN RIVER, DIKING AND SLOPE PROTECTION WORKS-PHASE 2, MEXICO, PAMPANGA

Region III, Region III

2025₱170.1M
Past target date (DPWH On-Going)
No sat.

PASIG-MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT, CONTRACT PACKAGE NO. 4-B, RIVER IMPROVEMENT WORKS ALONG UPPER MARIKINA RIVER (UPSTREAM OF MARIKINA BRIDGE) STA. 15+700 TO STA. 15+957 (PHASE 2), RIGHT BANK, MARIKINA CITY

Flood Control Management Cluster, Central Office

2022₱148.4M
Reported complete (100% progress, DPWH status On-Going)

Flood Control Works - Diking/Slope Protection of Pasig-Potrero River, Bacolor and Porac, Pampanga

PORAC (PAMPANGA), PAMPANGA, Region III

2023₱144.8M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION), PACKAGE 5, PROVINCE OF PAMPANGA

Region III, Region III

2020₱144.7M
Reported complete (DPWH)
View all 139 projects →

4. Implementation

Contract Amount

₱45,742,628.40

Progress

Reported complete (DPWH)

Start Date

March 24, 2016

Target End

September 19, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.