Bridges18DK0003

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-ILOG BRIDGE (B02424LZ) TAYABAS-LUCBAN-SAMPALOC-MAUBAN PORT ROAD

CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-ILOG BRIDGE (B02424LZ) TAYABAS-LUCBAN-SAMPALOC-MAUBAN PORT ROAD is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱8,918,000.00. Status: Reported complete (DPWH). Contractor on record: ZELAN CONST AND SUPPLY INC FORMERLY: ZELAN CONST AND SUPPLY. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Amot River, Burdeos, Quezon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Quezon 1st DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

80 projects · ₱502.6M total · 0 flags

4. Implementation

Contract Amount

₱8,918,000.00

Progress

Reported complete (DPWH)

Start Date

February 9, 2018

Target End

July 13, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.