Buildings and Facilities18DK0178

CONSTRUCTION OF TWO(2) STOREY TEN(10) CLASSROOM SCHOOL BUILDING @ KILOGAN ELEMENTARY SCHOOL, PATNANUNGAN, QUEZON

CONSTRUCTION OF TWO(2) STOREY TEN(10) CLASSROOM SCHOOL BUILDING @ KILOGAN ELEMENTARY SCHOOL, PATNANUNGAN, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱29,193,119.65. Status: Reported complete (DPWH). Contractor on record: ZELAN CONST AND SUPPLY INC FORMERLY: ZELAN CONST AND SUPPLY. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROIII-18-0032863 · · release to the district office, not itemized per project

    Possible match · score 0.69

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18DK0178 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2012-11-28 → 2012-11-28

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF TWO(2) STOREY TEN(10) CLASSROOM SCHOOL BUILDING @ KILOGAN ELEMENTARY SCHOOL, PATNANUNGAN, QUEZON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Seawall, San Lorenzo, Mauban, Quezon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0032863

₱0.00 · FY2018

Released to San Roque National High Ro School (Kapitangan National High School Annex-San Roque) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

80 projects · ₱502.6M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF TWO(2) STOREY TEN(10) CLASSROOM SCHOOL BUILDING @ PATNANUNGAN NORTE ELEMENTARY SCHOOL, PATNANUNGAN, QUEZON

Quezon 1st DEO, Region IV-A

2018₱29.0M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION: CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - GUMACA-PITOGO-MULANAY-SN NARCISO RD - K0217 + 038 - K0217 + 500, K0263 + 130 - K0263 + 855, K0281 + 732 - K0285 + 927

Quezon 3rd DEO, Region IV-A

2021₱27.4M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES MAUBAN-TIGNOAN ROAD (MAUBAN SIDE) K0167+038-K0167+081

Quezon 1st DEO, Region IV-A

2019₱26.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, NATIONAL BUILDING PROGRAM, BUILDING AND OTHER STRUCTURES, MULTIPURPOSE / FACILITIES, CONSTRUCTION OF GUINAYANGAN MEDICARE COMMUNITY HOSPITAL, GUINAYANGAN, QUEZON

Quezon 4th DEO, Region IV-A

2021₱24.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - MARIKINA-INFANTA RD - K0114 + 720 - K0114 + 980

Quezon 1st DEO, Region IV-A

2024₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF SEAWALL AT BRGY. SAN LORENZO, MAUBAN, QUEZON

Quezon 1st DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
View all 80 projects →

4. Implementation

Contract Amount

₱29,193,119.65

Progress

Reported complete (DPWH)

Start Date

November 27, 2018

Target End

September 2, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)QuezonPatnanunganKilogan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Dry conditions likelyPAGASA · 2026-10-07El Niño readiness →