Flood Control and Drainage24DK0080

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF SEAWALL AT BRGY. SAN LORENZO, MAUBAN, QUEZON

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF SEAWALL AT BRGY. SAN LORENZO, MAUBAN, QUEZON is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱14,846,579.63. Status: Reported complete (DPWH). Contractor on record: ZELAN CONST AND SUPPLY INC FORMERLY: ZELAN CONST AND SUPPLY. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures and Drainage System at Brgy. Sauyo, Quezon City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quezon 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

80 projects · ₱502.6M total · 0 flags

4. Implementation

Contract Amount

₱14,846,579.63

Progress

Reported complete (DPWH)

Start Date

June 3, 2024

Target End

November 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.