Flood Control and Drainage24PK0029

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF CHALIYONG - KUB-AO FLOOD CONT

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF CHALIYONG - KUB-AO FLOOD CONT is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱5,870,141.61. Status: Past target date (DPWH On-Going). Contractor on record: MA BUYAGAN CONST SERVICES. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Biyao River Flood Control Structures, Sta 159 + 635 - Sta 159 + 935 ( L / S ) , Talalang, Balbalan, Kalinga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0001358

₱186,833.00 · FY2024

Released to Regional Office - III (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

9 projects · ₱61.3M total · 0 flags

Other projects by this contractor

No sat.

Construction of Ngilin Flood Control along Chico River, Sta. 186+670 - Sta. 186+810 (R.S.), Ambato-Legleg, Tinglayan, Kalinga

TINGLAYAN (KALINGA), KALINGA, Cordillera Administrative Region

2024₱11.7M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONSTRUCTION OF LOCAL ROAD, TINGLAYAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2023₱9.9M
Reported complete (DPWH)
No sat.

Construction of Tabiong Flood Control along Chico River, Sta. 188+950 - Sta. 189+050 (LS), Poblacion, Tinglayan, Kalinga

TINGLAYAN (KALINGA), KALINGA, Cordillera Administrative Region

2024₱8.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG

Upper Kalinga DEO, Cordillera Administrative Region

2025₱7.8M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES CONSTRUCTION OF ACCESS ROAD IN BARANGAY BASAO, TINGLAYAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2024₱4.9M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) CONSTRUCTION OF ROAD, BARANGAY BASAO, TINGLAYAN, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2025₱4.9M
Past target date (DPWH On-Going)
View all 9 projects →

4. Implementation

Contract Amount

₱5,870,141.61

Progress

Past target date (DPWH On-Going)

Start Date

April 4, 2024

Target End

May 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.