GAA 2022 CSSP22D00106

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE USING ROCK NETTING ALONGLAIYA - MALABRIGO ROAD, SITIO NATUNGKAD - SITIO BIGA, BRGY. HUGOM,SAN JUAN, BATANGAS

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE USING ROCK NETTING ALONGLAIYA - MALABRIGO ROAD, SITIO NATUNGKAD - SITIO BIGA, BRGY. HUGOM,SAN JUAN, BATANGAS is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱144,686,101.49. Status: Reported complete (DPWH). Contractor on record: STRUKTURA TEKNIKA SERVICES CO. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱144,686,101.49

Progress

Reported complete (DPWH)

Start Date

August 4, 2022

Target End

May 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.