Bridges22CI0120

CONVERGENCE AND SPECIAL SUPPORT PROGRAM; SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; REPAIR/REHAB OF SAN ISIDRO BRIDGE, MAGALANG, PAMPANGA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM; SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; REPAIR/REHAB OF SAN ISIDRO BRIDGE, MAGALANG, PAMPANGA is a DPWH-tracked public work in Pampanga 3rd DEO, Region III. Reported contract value: ₱14,695,050.17. Status: Reported complete (DPWH). Contractor on record: N M D CONST. Figures trace to dpwh.

Pampanga 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Santol Creek, San Jose Section, Brgy. San Jose, Floridablanca, Pampanga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0008163

₱38,865,479.00 · FY2022

Released to Regional Office XI - Proper (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,695,050.17

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

August 20, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.