Roads20K00046

ROAD WIDENING, CAMIGUIN CIRCUMFERENTIAL RD - K0002+732 - K0002+817, K0002+827 - K0002+927, K0004+649 - K0004+850, K0004+918 - K0004+961, K0009+597 - K0009+697, K0009+716 - K0009+812, K0011+848 - K0012+177, K0012+218 - K0012+310, K0013+797 - K0014+358, ...

ROAD WIDENING, CAMIGUIN CIRCUMFERENTIAL RD - K0002+732 - K0002+817, K0002+827 - K0002+927, K0004+649 - K0004+850, K0004+918 - K0004+961, K0009+597 - K0009+697, K0009+716 - K0009+812, K0011+848 - K0012+177, K0012+218 - K0012+310, K0013+797 - K0014+358, ... is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱128,291,401.02. Status: Reported complete (DPWH). Contractor on record: JEJOR'S CONST CORP. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱128,291,401.02

Progress

Reported complete (DPWH)

Start Date

December 7, 2020

Target End

May 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.