Flood Control and Drainage21EI0027

CONSTRUCTION OF BONGABONG RIVER CONTROL, BARANGAY SAN JOSE SECTION, BONGABONG, ORIENTAL MINDORO

CONSTRUCTION OF BONGABONG RIVER CONTROL, BARANGAY SAN JOSE SECTION, BONGABONG, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱24,499,996.77. Status: Reported complete (DPWH). Contractor on record: E E CONST. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱2,861,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in Bongabong River, Mapang Section, Bongabong, Oriental Mindoro
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-21-0002656

₱163,085,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱24,499,996.77

Progress

Reported complete (DPWH)

Start Date

February 23, 2021

Target End

October 20, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.