Construction of Slope Protection Structure23DQ0106

Construction of Slope and Flood Protection Structure along Carmona River, Phase 2, Carmona, Cavite

Construction of Slope and Flood Protection Structure along Carmona River, Phase 2, Carmona, Cavite is a DPWH-tracked public work in CITY OF CARMONA (CAVITE), CAVITE, Region IV-A. Reported contract value: ₱89,092,693.05. Status: Reported complete (DPWH). Contractor on record: AARCON BUILDERS. Figures trace to sumbong.

CITY OF CARMONA (CAVITE), CAVITE, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱90,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope and Flood Protection Structure along Carmona River, Phase 1, Carmona, Cavite
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cavite 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱89,092,693.05

Progress

Reported complete (DPWH)

Start Date

June 6, 2023

Target End

May 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.