Construction of Flood Mitigation Structure22AD0064

Construction of Sorioan River Control Structure, Salcedo, Ilocos Sur

Construction of Sorioan River Control Structure, Salcedo, Ilocos Sur is a DPWH-tracked public work in SALCEDO (BAUGEN) (ILOCOS SUR), ILOCOS SUR, Region I. Reported contract value: ₱48,999,995.79. Status: Reported complete (DPWH). Contractor on record: VILLAR GEN CONST AND SUPPLIES. Figures trace to sumbong.

SALCEDO (BAUGEN) (ILOCOS SUR), ILOCOS SUR, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Lingsat, Bantay, Ilocos Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-22-0010140

₱19,203,297.00 · FY2022

Released to Division of South Cotabato (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002719

₱1,343,647,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003111

₱145,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

493 projects · ₱8.0B total · 42 flags

4. Implementation

Contract Amount

₱48,999,995.79

Progress

Reported complete (DPWH)

Start Date

April 4, 2022

Target End

December 30, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.