Construction of Flood Mitigation Structure24JD0016

Construction of Flood Control Structure along Palandok River at Polandok Br. (Downstream - Salug Side), Salug, Zamboanga del Norte

Construction of Flood Control Structure along Palandok River at Polandok Br. (Downstream - Salug Side), Salug, Zamboanga del Norte is a DPWH-tracked public work in SALUG (ZAMBOANGA DEL NORTE), ZAMBOANGA DEL NORTE, Region IX. Reported contract value: ₱44,100,000.00. Status: Reported complete (DPWH). Contractor on record: LONG ISLAND BUILDERS & CONST. Figures trace to sumbong.

SALUG (ZAMBOANGA DEL NORTE), ZAMBOANGA DEL NORTE, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Palandok River at Polandok Br. ( Downstream - Salug Side ) , Salug, Zamboanga del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-24-0005040

₱375,603.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0003725

₱2,468,519.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0007625

₱1,296,481.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0003726

₱193,302.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0007627

₱119,751.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱44,100,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

December 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.