Construction of Flood Mitigation Structure22A00177

Construction of Flood Mitigation Structure along Vintar River (Bislak River), Brgy. Alsem, Sitio Di Tulang, Vintar, Ilocos Norte

Construction of Flood Mitigation Structure along Vintar River (Bislak River), Brgy. Alsem, Sitio Di Tulang, Vintar, Ilocos Norte is a DPWH-tracked public work in VINTAR (ILOCOS NORTE), ILOCOS NORTE, Region I. Reported contract value: ₱95,039,995.11. Status: Reported complete (DPWH). Contractor on record: JCA CONST AND CONST SUPPLY / EGB CONST CORP FORMERLY: EGB CONST. Figures trace to sumbong.

VINTAR (ILOCOS NORTE), ILOCOS NORTE, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱44,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Vintar River (Bislak River), Brgy. Alsem, Sitio Namnama, Vintar, Ilocos Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-22-0005987

₱1,486,000.00 · FY2022

Released to Cebu 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002978

₱1,132,084,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003109

₱100,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0011001

₱100,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002617

₱25,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱95.0M total · 0 flags

4. Implementation

Contract Amount

₱95,039,995.11

Progress

Reported complete (DPWH)

Start Date

April 1, 2022

Target End

November 23, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.