Buildings and Facilities17BD0039

LIP: CONSTRUCTION OF 2 CLASSROOMS, BAYO ELEMENTARY SCHOOL, IGUIG, CAGAYAN 3RD LD

LIP: CONSTRUCTION OF 2 CLASSROOMS, BAYO ELEMENTARY SCHOOL, IGUIG, CAGAYAN 3RD LD is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱1,825,114.78. Status: Reported complete (DPWH). Contractor on record: M C TAGUBA CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱44,781,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Minanga Norte Flood Control System (Downstream), Sta. 0+221 – Sta. 0+382, Minanga Norte, Iguig, Cagayan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0025300

₱5,300,000.00 · FY2017

Released to Regional Office - Proper (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,825,114.78

Progress

Reported complete (DPWH)

Start Date

February 21, 2017

Target End

May 6, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.