Roads22PF0057

CONCRETING OF SITIO LAY-ODAN TO SITIO BANEY, BRGY. SEBANG FMR, BRGY. SEBANG, BUGUIAS, BENGUET

CONCRETING OF SITIO LAY-ODAN TO SITIO BANEY, BRGY. SEBANG FMR, BRGY. SEBANG, BUGUIAS, BENGUET is a DPWH-tracked public work in Benguet 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱12,386,652.73. Status: Reported complete (DPWH). Contractor on record: JYP GEN CONST. Figures trace to dpwh.

Benguet 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Nabalicong, Natubleng, Buguias, Benguet
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-22-0014577

₱25,899,956.00 · FY2022

Released to Regional Office - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

13 projects · ₱165.0M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF SITIO EKIP TO SITIO SEB-ITAN FLOOD CONTROL STA. 3+991 - STA. 4+382 (L.S.), STA. 3+950 - STA. 4+208 (R.S.), BUGUIAS, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2021₱29.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF LOO FLOOD CONTROL

Benguet 2nd DEO, Cordillera Administrative Region

2020₱29.3M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE TERTIARY ROADS KIANGAN-TINOC-BUGUIAS ROAD, K0354+670 K0354+690, K0355+591-K0355+615, K0355+780-K0355+914, K0357+312-K0357+391, K0359+612-K0359+648

Benguet 2nd DEO, Cordillera Administrative Region

2021₱25.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ALAKAN FLOOD CONTROL STA. 0+155 - STA. 0+386 (L.S.), STA. 0+261 - STA. 0+323 (R.S.), STA. 0+356 - STA. 0+443 (R.S.), STA. 0+692 - STA. 0+745 (L.S.), STA. 0+958 - STA. 1+000 (B.S.) BUGUIAS, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2021₱19.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS (TERTIARY ROAD) ALONG KIANGAN-TINOC-BUGUIAS ROAD K0354+(-208) - K0354+(-163), K0358+450 - K

Benguet 2nd DEO, Cordillera Administrative Region

2020₱18.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF IBISAN KAMANBAGANG ROAD, SEBANG, BUGUIAS, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2022₱9.8M
Reported complete (DPWH)
View all 13 projects →

4. Implementation

Contract Amount

₱12,386,652.73

Progress

Reported complete (DPWH)

Start Date

June 1, 2022

Target End

November 18, 2022