Construction of Flood Mitigation Structure22BB0016

Construction of Flood Control Structure along Cagayan River, Centro Norte Section 2, Gattaran, Cagayan

Construction of Flood Control Structure along Cagayan River, Centro Norte Section 2, Gattaran, Cagayan is a DPWH-tracked public work in GATTARAN (CAGAYAN), CAGAYAN, Region II. Reported contract value: ₱24,499,889.95. Status: Reported complete (DPWH). Contractor on record: TJMT CONST. Figures trace to sumbong.

GATTARAN (CAGAYAN), CAGAYAN, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cagayan River, Centro Norte Section 1, Gattaran, Cagayan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-22-0007797

₱107,065,000.00 · FY2022

Released to Cagayan 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002959

₱446,985,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0003637

₱1,122,803.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-22-0003638

₱100,632.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

227 projects · ₱6.0B total · 35 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS MAHARLIKA HIGHWAY (CAGAYAN VALLEY ROAD) - K0541+000 - K0541+533, K0548+000 - K0548+920, K0549+050 - K0549+940, K0550+094 - K0550+605.50

Region II, Region II

2025₱138.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF CONCRETE ROAD - GATTARAN DIVERSION ROAD, PACKAGE 1, GATTARAN, CAGAYAN

Cagayan 1st DEO, Region II

2025₱135.1M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - NAGANTATAPIAN BRIDGE (B01094LZ) ALONG CAGAYAN VALLEY ROAD

Region II, Region II

2023₱119.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE & RELIABLE NATL RD SYSTEM - ASSET PRESERVATN - REHAB/ RECONST/ UPGRADING OF DAMAGED PAVED RDS - TERTIARY ROADS - REHABILITATION OF PAVED ROAD - BBDSMR- K0519+331-K0519+600.50 TO K0546+000-K0547+1012.5, BAGGAO, CAGAYAN

Cagayan 1st DEO, Region II

2024₱102.4M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF SEAWALL, BARANGAY PADDAYA, APARRI, CAGAYAN

Cagayan 1st DEO, Region II

2025₱96.5M
Past target date (DPWH On-Going)

Construction of Flood Control Structure along Cagayan River, Aguigican, Gattaran, Cagayan, Package 1

GATTARAN (CAGAYAN), CAGAYAN, Region II

2024₱96.5M
Reported complete (DPWH)
View all 227 projects →

4. Implementation

Contract Amount

₱24,499,889.95

Progress

Reported complete (DPWH)

Start Date

February 2, 2022

Target End

April 5, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.