Contingent Fund 2019 Extended20DF0198

CONSTRUCTION/IMPROVEMENT/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT GREEN MARK, MALAGASANG II B, IMUS; REPAIR/REHAB/COMPLETION OF MULTI-PURPOSED BUILDING (COVERED COURT) AT GREENGATE MALAGASANG II B, IMUS; REPAIR/REHAB/COMPLETION OF MULTI

CONSTRUCTION/IMPROVEMENT/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT GREEN MARK, MALAGASANG II B, IMUS; REPAIR/REHAB/COMPLETION OF MULTI-PURPOSED BUILDING (COVERED COURT) AT GREENGATE MALAGASANG II B, IMUS; REPAIR/REHAB/COMPLETION OF MULTI is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱12,545,000.00. Status: Reported complete (DPWH). Contractor on record: FROMARC BUILDERS. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

61 projects · ₱1.5B total · 0 flags

Other projects by this contractor

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONST OF REVETMENT ALONG ILANG-ILANG RIVER BRGY.ALAPAN SEC PHASE IV

Cavite 1st DEO, Region IV-A

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERSCONST OF REVETMENT ALONG JULIAN RIVER, BRGY MALAGASANG I-B, IMUS,

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 :PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROG CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS CONST OF REVETMENT ALONG JULIAN RIVER PHASE 1, BRGY. ANABU I-B IMUS

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERSCONST OF REVETMENT ALONG JULIAN RIVER, BRGY ANABU I-D, IMUS, CAV

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARSADANG BAGO - MALAGASANG DIVERSION ROAD, ALAPAN - CARSADANG BAGO SECTION, CAVITE

Cavite 1st DEO, Region IV-A

2024₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARSADANG BAGO - MALAGASANG DIVERSION ROAD, BUCANDALA SECTION, SEGMENT 2, CAVITE

Cavite 1st DEO, Region IV-A

2024₱77.2M
Reported complete (DPWH)
View all 61 projects →

4. Implementation

Contract Amount

₱12,545,000.00

Progress

Reported complete (DPWH)

Start Date

October 20, 2020

Target End

April 17, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.