ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONST OF REVETMENT ALONG ILANG-ILANG RIVER BRGY.ALAPAN SEC PHASE IV
ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONST OF REVETMENT ALONG ILANG-ILANG RIVER BRGY.ALAPAN SEC PHASE IV is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱96,500,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FROMARC BUILDERS. Figures trace to dpwh.
Total Contract Cost