Buildings and Facilities24DD0201

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. QUEZON, LIPA CITY, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. QUEZON, LIPA CITY, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱4,875,750.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: P-SQUARE CONTRACTING. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bawi and Banaba Creek, Padre Garcia, Batangas
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0019178

₱0.00 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

62 projects · ₱324.4M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN LUCAS, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱29.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION/ IMPROVEMENT OF MULTI-PURPOSE BUILDING IN VARIOUS BARANGAYS, IBAAN, BATANGAS

Batangas 4th DEO, Region IV-A

2019₱24.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (BUILDING 1), PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱10.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONCRETING OF FARM-TO-MILL ROAD, BRGY. MABALOR, IBAAN, BATANGAS

Batangas 4th DEO, Region IV-A

2017₱10.3M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL ROADS, REHABILITATION/ IMPROVEMENT OF ROSARIO-TAYSAN ROAD, ROSARIO, BATANGAS

Batangas 4th DEO, Region IV-A

2021₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING IN PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2023₱9.6M
Reported complete (DPWH)
View all 62 projects →

4. Implementation

Contract Amount

₱4,875,750.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 24, 2024

Target End

August 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.