Construction of Flood Mitigation Structure22IH0026

Construction (Extension) of Catarman Flood Control Structures (Catarman River Basin), Brgy. Sampaguita, Jose Abad Santos, Baybay, Catarman, Northern Samar

Construction (Extension) of Catarman Flood Control Structures (Catarman River Basin), Brgy. Sampaguita, Jose Abad Santos, Baybay, Catarman, Northern Samar is a DPWH-tracked public work in CATARMAN (CAPITAL) (NORTHERN SAMAR), NORTHERN SAMAR, Region VIII. Reported contract value: ₱42,254,877.86. Status: Reported complete (DPWH). Contractor on record: SAL CONST / CDU CONST. Figures trace to sumbong.

CATARMAN (CAPITAL) (NORTHERN SAMAR), NORTHERN SAMAR, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱43,125,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Extension) of Catarman Flood Control Structures (Catarman River Basin), Brgy. Sampaguita, Jose Abad Santos, Baybay, Catarman, Northern Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0002496

₱244,688,407.00 · FY2022

Released to Northern Samar 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003182

₱192,636,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0013001

₱27,584.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱42,254,877.86

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

October 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.