Roads23JF0023

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - ROAD CONCRETING JUNCTION NATIONAL HIGHWAY AT BRGY. COLORAN TO BRGY. PARUK IN S

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - ROAD CONCRETING JUNCTION NATIONAL HIGHWAY AT BRGY. COLORAN TO BRGY. PARUK IN S is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱12,225,000.50. Status: Reported complete (DPWH). Contractor on record: BELVIC ENT. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (revetment wall) along Sibuguey River (upstream), Sta. 0+000.00 - Sta. 0+417.00, Barangay Sampoli A, Diplahan, Zamboanga Sibugay (Package 2)
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0023800

₱6,342,353.00 · FY2023

Released to 0000000 Central Bicol State - University of Agriculture (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱12,225,000.50

Progress

Reported complete (DPWH)

Start Date

February 14, 2023

Target End

May 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.