Flood Control and Drainage24IA0021

CONSTRUCTION OF GUERON FLOOD CONTROL ALONG NAVAL-CAIBIRAN CROSS COUNTRY ROAD, PHASE I, NAVAL, BILIRAN

CONSTRUCTION OF GUERON FLOOD CONTROL ALONG NAVAL-CAIBIRAN CROSS COUNTRY ROAD, PHASE I, NAVAL, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱26,578,803.68. Status: Reported complete (DPWH). Contractor on record: SUNRISE BUILDERS 39757. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱27,712,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Gueron Flood Control along Naval - Caibiran Cross Country Road, Phase I, Naval, Biliran
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0016293

₱168,381.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱26,578,803.68

Progress

Reported complete (DPWH)

Start Date

February 11, 2024

Target End

November 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.