Flood Control and Drainage24IA0065

CONSTRUCTION OF ALMERIA FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE 2, ALMERIA, BILIRAN

CONSTRUCTION OF ALMERIA FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE 2, ALMERIA, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱28,740,473.90. Status: Past target date (DPWH On-Going). Contractor on record: SUNRISE BUILDERS. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Almeria Flood Control along Almeria Bypass Road, Almeria, Biliran
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0016293

₱168,381.00 · FY2024

Released to Tarlac 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱28,740,473.90

Progress

Past target date (DPWH On-Going)

Start Date

February 28, 2024

Target End

October 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.