Flood Control and Drainage20OD0134

CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANK OF CREEKS ALONG KABATUHAN ROAD, BRGY. 168, CALOOCAN CITY

CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANK OF CREEKS ALONG KABATUHAN ROAD, BRGY. 168, CALOOCAN CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱28,604,260.39. Status: Reported complete (DPWH). Contractor on record: PERSAN CONST INC FORMERLY: PERSAN CONST. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Bank of Creeks along Kabatuhan Road, Brgy. 168 , Caloocan City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-20-0000649

₱0.00 · FY2020

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

170 projects · ₱10.0B total · 10 flags

4. Implementation

Contract Amount

₱28,604,260.39

Progress

Reported complete (DPWH)

Start Date

November 20, 2020

Target End

September 15, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.