Construction of Flood Mitigation Structure23BB0112

Construction of Seawall, Brgy. Santa Maria, Buguey, Cagayan

Construction of Seawall, Brgy. Santa Maria, Buguey, Cagayan is a DPWH-tracked public work in BUGUEY (CAGAYAN), CAGAYAN, Region II. Reported contract value: ₱19,754,081.38. Status: Reported complete (DPWH). Contractor on record: REYROSE CONST. Figures trace to sumbong.

BUGUEY (CAGAYAN), CAGAYAN, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Union Flood Control along Brgy. Cadcadir River, Claveria in Cagayan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-23-002636

₱25,961,133.00 · FY2023

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱19,754,081.38

Progress

Reported complete (DPWH)

Start Date

April 4, 2023

Target End

November 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.