Construction of Flood Mitigation Structure23FA0040

Construction of Quinale Seawall, Tabaco City, Albay Phase II

Construction of Quinale Seawall, Tabaco City, Albay Phase II is a DPWH-tracked public work in CITY OF TABACO (ALBAY), ALBAY, Region V. Reported contract value: ₱41,650,000.00. Status: Reported complete (DPWH). Contractor on record: SANRHO BUILDERS INC FOR SANRHO CONST AND SUPPL / 3RB CONST & SUPPLY. Figures trace to sumbong.

CITY OF TABACO (ALBAY), ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tayhi River Control/Flood Mitigation at Barangay Cormidal, Tabaco City, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0021169

₱646,190.00 · FY2023

Released to Bagamanoc Rural Development High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱41,650,000.00

Progress

Reported complete (DPWH)

Start Date

May 26, 2023

Target End

March 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.