ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY GUINACUTAN TO BARANGAY NAPI
ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY GUINACUTAN TO BARANGAY NAPI is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱47,766,536.32. Status: Past target date (DPWH On-Going). Contractor on record: 128 DRAGON CONST AND SUPPLIES. Figures trace to dpwh.
Satellite images processing — before/after tiles will appear here after the next batch run.
Total Contract Cost