Buildings and Facilities23FB0012

CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) PHASE 2, BRGY. BAÑAG, DARAGA, ALBAY

CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) PHASE 2, BRGY. BAÑAG, DARAGA, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱4,800,644.75. Status: Past target date (DPWH On-Going). Contractor on record: NEXT GENERATION CONST AND SUPPLY CORP. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Villahermosa, Daraga, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0021169

₱646,190.00 · FY2023

Released to Bagamanoc Rural Development High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,800,644.75

Progress

Past target date (DPWH On-Going)

Start Date

June 19, 2023

Target End

October 16, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.