Buildings and Facilities21HH0084

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTI PURPOSE / FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY PARIL, CEBU CITY

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTI PURPOSE / FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY PARIL, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱959,739.92. Status: Reported complete (DPWH). Contractor on record: SQUARE ONE BUILDERS. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱25,353,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Barangay Suba, Cebu City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-21-0017348

₱87,914,298.00 · FY2021

Released to Central Office (NIA) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

41 projects · ₱152.9M total · 0 flags

4. Implementation

Contract Amount

₱959,739.92

Progress

Reported complete (DPWH)

Start Date

March 31, 2021

Target End

May 29, 2021

5. Audit