Flood Control and Drainage20JA0035

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAAZ RIVER, SAN RAMON, BRGY. TALISAYAN, ZAMBOANGA CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAAZ RIVER, SAN RAMON, BRGY. TALISAYAN, ZAMBOANGA CITY is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱29,169,043.58. Status: Reported complete (DPWH). Contractor on record: JM2K CONST. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Saaz River, San Ramon, Brgy. Talisayan, Zamboanga City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-20-0015981

₱688,000.00 · FY2020

Released to Quirico G. Manzano Memorial National High School (Caningay National High School - Candoni Extension) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

20 projects · ₱339.5M total · 1 flags

Other projects by this contractor

View all 20 projects →

4. Implementation

Contract Amount

₱29,169,043.58

Progress

Reported complete (DPWH)

Start Date

February 14, 2020

Target End

March 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.