Roads21LG0109

CONCRETING OF BRGY. DON MARTIN MARUNDAN FMR PHASE II, BRGY. DON MARTIN MARUNDAN, MATI CITY, DAVAO ORIENTAL

CONCRETING OF BRGY. DON MARTIN MARUNDAN FMR PHASE II, BRGY. DON MARTIN MARUNDAN, MATI CITY, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 2nd DEO, Region XI. Reported contract value: ₱12,715,120.52. Status: Reported complete (DPWH). Contractor on record: FAJR CONST PARTS AND SUPPLY. Figures trace to dpwh.

Davao Oriental 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Brgy. Sanghay River, Mati City, Davao Oriental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱404,461,000.00 · FY2021

Released to Cavite 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱12,715,120.52

Progress

Reported complete (DPWH)

Start Date

June 24, 2021

Target End

October 15, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.