Construction of Revetment24IA0032

Construction of Flood Control Structure, Barangay Agpangi, Naval, Biliran

Construction of Flood Control Structure, Barangay Agpangi, Naval, Biliran is a DPWH-tracked public work in NAVAL (CAPITAL) (BILIRAN), BILIRAN, Region VIII. Reported contract value: ₱9,791,565.03. Status: Reported complete (DPWH). Contractor on record: MKB BUILDERS AND SUPPLY. Figures trace to sumbong.

NAVAL (CAPITAL) (BILIRAN), BILIRAN, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Agpangi, Naval, Biliran
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-24-0011737

₱57,620,507.20 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008479

₱1,467,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0002253

₱1,340,225.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0001232

₱289,442.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008480

₱135,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,791,565.03

Progress

Reported complete (DPWH)

Start Date

February 14, 2024

Target End

June 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.