Roads21DE0019

LOCAL INFRASTRUCTURE PROGRAM-CONCRETING OF ROAD,BARANGAY 13,POBLACION 1,TINGLOY,BATANGAS

LOCAL INFRASTRUCTURE PROGRAM-CONCRETING OF ROAD,BARANGAY 13,POBLACION 1,TINGLOY,BATANGAS is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱1,980,000.00. Status: Reported complete (DPWH). Contractor on record: GREENFIELD CONST. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱36,552,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Along Sawang River (Sitio Bungahan II and Sitio Ulopong), Lobo, Batangas
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱407,327,000.00 · FY2021

Released to Batangas 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

376 projects · ₱2.4B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF RIVER CONTROL STRUCTURE, BARANGAY MANGHINAO, BAUAN, BAT

Batangas 2nd DEO, Region IV-A

2025₱47.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY TABANGAO, A

Batangas 2nd DEO, Region IV-A

2024₱46.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), MABINI, BATANGAS

Batangas 2nd DEO, Region IV-A

2022₱39.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE FACILITY (SPORTS AND CULTURAL CENTER), SAN JUAN, BATANGAS

Batangas 4th DEO, Region IV-A

2023₱33.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING IN THE MUNICIPALITY OF PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2023₱33.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, BIGA-APAR ROAD, BARANGAY BIGA TO APAR, LOBO, BATANGAS

Batangas 2nd DEO, Region IV-A

2022₱29.7M
Reported complete (DPWH)
View all 376 projects →

4. Implementation

Contract Amount

₱1,980,000.00

Progress

Reported complete (DPWH)

Start Date

February 3, 2021

Target End

April 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.