Buildings and Facilities24KA0084

CONSTRUCTION OF TWO (2) STOREY EIGHT (8) CLASSROOM SCHOOL BUILDING -LITTLE BAGUIO ELEMENTARY SCHOOL, BARANGAY LITTLE BAGUIO, SAN FERNANDO, BUKIDNON, BARANGAY LITTLE BAGUIO, SAN FERNANDO, BUKIDNON 2ND LD

CONSTRUCTION OF TWO (2) STOREY EIGHT (8) CLASSROOM SCHOOL BUILDING -LITTLE BAGUIO ELEMENTARY SCHOOL, BARANGAY LITTLE BAGUIO, SAN FERNANDO, BUKIDNON, BARANGAY LITTLE BAGUIO, SAN FERNANDO, BUKIDNON 2ND LD is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱25,090,000.00. Status: Reported complete (DPWH). Contractor on record: H. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Sinanglanan, Malaybalay City, Bukidnon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-24-0005803

₱1,716,524.00 · FY2024

Released to The President's Offices (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

60 projects · ₱437.1M total · 0 flags

4. Implementation

Contract Amount

₱25,090,000.00

Progress

Reported complete (DPWH)

Start Date

April 24, 2024

Target End

February 2, 2025

5. Audit