Buildings and Facilities20CG0258

CONSTRUCTION OF TWO (2) STOREY, TEN (10) CLASSROOM SCHOOL BUILDING AT SAN SIMON ELEMENTARY SCHOOL, SAN SIMON, PAMPANGA

CONSTRUCTION OF TWO (2) STOREY, TEN (10) CLASSROOM SCHOOL BUILDING AT SAN SIMON ELEMENTARY SCHOOL, SAN SIMON, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱24,683,317.20. Status: Reported complete (DPWH). Contractor on record: N-22 CONST AND TRADING. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Porac River, Jalung, Pampanga
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-20-0005067

₱3,596,871.00 · FY2020

Released to Sta. Ana National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

130 projects · ₱898.3M total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM: REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MANILA NORTH RD - K0057+571 - K0057+864, K0059+650 - K0059+970, K0060+191 - K0061+220, PAMPANGA

Pampanga 1st DEO, Region III

2020₱91.1M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/ FACILITIES - REHABILITATION OF PANQUIARY RIVER CONTROL STRUCTURE, STA. MONICA, SAN SIMON, PAMPANGA

Pampanga 1st DEO, Region III

2022₱27.8M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM: CONSTRUCTION/ UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - TERTIARY ROADS - STO. TOMAS _MINALIN RD (MINALIN - MACABEBE SECT) - K0071+000 - K0071+636, K0072+056 - K0072+474, MINALIN, PAMPANGA

Pampanga 1st DEO, Region III

2020₱26.7M
Reported complete (DPWH)
No sat.

CONCRETING OF FARM TO MARKET ROAD AT BRGY. PALIGUE, APALIT, PAMPANGA

Pampanga 1st DEO, Region III

2025₱23.6M
Ongoing (DPWH-reported)
No sat.

ASSET PRESERVATION PROGRAM: REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - BALIWAG - CANDABA - STA ANA RD - K0064+000 - K0064+312, K0065+020 - K0065+400

Pampanga 1st DEO, Region III

2023₱19.7M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM: REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - STO. TOMAS - MINALIN RD (MINALIN - MACABEBE SECT) - K0072+060.4 - K0072+647.6

Pampanga 1st DEO, Region III

2023₱19.3M
Reported complete (DPWH)
View all 130 projects →

4. Implementation

Contract Amount

₱24,683,317.20

Progress

Reported complete (DPWH)

Start Date

December 14, 2020

Target End

June 6, 2021

5. Audit