Buildings and Facilities24MH0070

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY VILLAMONTE, LEBAK, SULTAN KUDARAT

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY VILLAMONTE, LEBAK, SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 2nd DEO, Region XII. Reported contract value: ₱1,974,545.65. Status: Reported complete (DPWH). Contractor on record: JV CONSTECH. Figures trace to dpwh.

Sultan Kudarat 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Tran, Lebak, Sultan Kudarat
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0010131

₱42,148,921.00 · FY2024

Released to Sultan Kudarat 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,974,545.65

Progress

Reported complete (DPWH)

Start Date

January 31, 2024

Target End

July 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.