Flood Control and Drainage21FO0045

REHABILITATION/IMPROVEMENT OF BACOLOD FLOOD CONTROL STRUCTURE (RIGHT SIDE FACING DOWN STREAM OF BACOLOD BRIDGE PHASE II), LIBON, ALBAY

REHABILITATION/IMPROVEMENT OF BACOLOD FLOOD CONTROL STRUCTURE (RIGHT SIDE FACING DOWN STREAM OF BACOLOD BRIDGE PHASE II), LIBON, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱9,602,608.98. Status: Past target date (DPWH On-Going). Contractor on record: NEXT GENERATION CONST AND SUPPLY CORP. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Bacolod Flood Control Structure (Right Side Facing Downstream of Bacolod Bridge Phase III), Libon, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱445,768,000.00 · FY2021

Released to Laguna 3rd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,602,608.98

Progress

Past target date (DPWH On-Going)

Start Date

September 27, 2021

Target End

January 9, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.