Roads25DC0235

OPENING AND CONCRETING OF BRGY. LUMANG LIPA FMR, BRGY. LUMANG LIPA, MATAAS NA KAHOY, BATANGAS

OPENING AND CONCRETING OF BRGY. LUMANG LIPA FMR, BRGY. LUMANG LIPA, MATAAS NA KAHOY, BATANGAS is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱14,543,229.00. Status: Past target date (DPWH On-Going). Contractor on record: PRIME MOVER'S PHILS CONST AND SUPPLIES INC. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. New Danglayan, Bauan, Batangas
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-25-0008577

₱372,885.00 · FY2025

Released to Ilocos Training and Regional Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

57 projects · ₱338.1M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY LOOB PROVINCIAL/NATIONAL ROAD, BARANG

Batangas 3rd DEO, Region IV-A

2023₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, PUROK 5, BARANGAY UPA, MATAAS NA KAHOY, BAT

Batangas 3rd DEO, Region IV-A

2025₱14.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) AT BARANGAY 3, MATAASNAKAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY 1, MATAASNAKAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY LOOB, MATAASNAKAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM. BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF MULTI-PURPOSE BUILDING (C0VERED COURT), CENTRAL SCHOOL, BARANGAY 4, MATAASNAKAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2025₱9.7M
Past target date (DPWH On-Going)
View all 57 projects →

4. Implementation

Contract Amount

₱14,543,229.00

Progress

Past target date (DPWH On-Going)

Start Date

August 14, 2025

Target End

January 10, 2026

5. Audit