Buildings and Facilities24KF0030

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. POBLACION, SAPAD, LANAO DEL NORTE

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING BRGY. POBLACION, SAPAD, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱9,684,542.02. Status: Reported complete (DPWH). Contractor on record: AL-NOORWAY CORP. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Big Banisilon, Tangcal, Lanao del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVIII-24-0012143

₱19,659,000.00 · FY2024

Released to Lanao del Norte 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

124 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱9,684,542.02

Progress

Reported complete (DPWH)

Start Date

February 19, 2024

Target End

July 7, 2024

5. Audit