Roads24D00111

FY 2024 DPWH INFRASTRUCTURE PROG.-ORGANIZATIONAL OUTCOME 1:ENSURE SAFE & RELIABLE NATL ROAD SYSTEM-ASSET PRESERVATION PROG.-CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL RDS - PRIMARY RDS-DAANG MAHARLIKA (LZ)-K0088+910-K0090+042

FY 2024 DPWH INFRASTRUCTURE PROG.-ORGANIZATIONAL OUTCOME 1:ENSURE SAFE & RELIABLE NATL ROAD SYSTEM-ASSET PRESERVATION PROG.-CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL RDS - PRIMARY RDS-DAANG MAHARLIKA (LZ)-K0088+910-K0090+042 is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱114,083,023.10. Status: Past target date (DPWH On-Going). Contractor on record: ALL EML CONST CORP FORMERLY: E M L CONST. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

66 projects · ₱3.2B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADLUCBAN DIVERSION RD, QUEZON

Region IV-A, Region IV-A

2025₱327.6M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS, BACOLOR-PORAC ACCESS ROAD (PORAC SECTION)-PACKAGE 2, PROVINCE OF PAMPANGA

Region III, Region III

2023₱162.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; CONSTRUCTION OF ABACAN ROAD DIKE (LEFT SIDE) UPSTREAM OF HENSONVILLE BRIDGE, ANGELES

Pampanga 3rd DEO, Region III

2024₱130.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) K0076+(-010)-K0077+920

Pampanga 2nd DEO, Region III

2025₱124.2M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; CONSTRUCTION OF ROAD DIKE WITH SLOPE PROTECTION ALONG ABACAN RIVER AT BARANGAY ANUNA

Pampanga 3rd DEO, Region III

2024₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES; CONSTRUCTION OF ROAD DIKE WITH SLOPE PROTECTION ALONG ABACAN RIVER AT BARANGAY AMSIC

Pampanga 3rd DEO, Region III

2024₱96.5M
Reported complete (DPWH)
View all 66 projects →

4. Implementation

Contract Amount

₱114,083,023.10

Progress

Past target date (DPWH On-Going)

Start Date

April 24, 2024

Target End

December 4, 2024

5. Audit