GAA 2025 SSP25PJ0056

25PJ0056: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM- (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF LGU ALFONSO LISTA MULTI-PURPOSE BUILDING (COMPLETION), STA. MARIA, ALFONSO LISTA, IFUGA

25PJ0056: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM- (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF LGU ALFONSO LISTA MULTI-PURPOSE BUILDING (COMPLETION), STA. MARIA, ALFONSO LISTA, IFUGA is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱4,938,677.27. Status: Past target date (DPWH On-Going). Contractor on record: MR-G CONST. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Poblacion Pakawit Communal Irrigation System (CIS), Tinoc, Ifugao
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-25-0018364

₱0.00 · FY2025

Released to Philippine Sports Commission (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

31 projects · ₱144.5M total · 0 flags

Other projects by this contractor

No sat.

23PJ0045: REPAIR/REHABILITATION ANDCONSTRUCTION OF FARM-TO-MARKET ROADS IN DESIGNATED KEY PRODUCTIONAREAS-CONCRETING OF SITIO ALWASA PUMPHOUSE TO FISHPORT, BRGY. STO.DOMINGO FMR, BRGY. STO. DOMINGO, ALFONSO LISTA, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱11.9M
Reported complete (DPWH)
No sat.

24PJ0044-CONCRETING OF BALANGBANG TO BANAO, FMR, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱9.9M
Reported complete (DPWH)
No sat.

24PJ0045-CONCRETING OF SITIO TAMANG, BRGY. DAMAG FMR BRGY. DAMAG, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱9.9M
Reported complete (DPWH)
No sat.

23PJ0041: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BRGY. UBAO, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱9.9M
Reported complete (DPWH)
No sat.

25PJ0031: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP)-ACCESS ROAD LEADING TO AMMUNG FESTIVAL, YAO JIA XI DRAGON FRUIT FARM, DOMINGO

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTIPURPOSE BUILDING IN KILING, ALFONSO LISTA, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2022₱5.0M
Reported complete (DPWH)
View all 31 projects →

4. Implementation

Contract Amount

₱4,938,677.27

Progress

Past target date (DPWH On-Going)

Start Date

July 7, 2025

Target End

January 2, 2026

5. Audit