Roads17N00031

CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING ROADS, INCLUDING ROW, BDRY. BUKIDNON/AGUSAN DEL NORTE 1ST LD, PACKAGE 2, LAS NIEVES, AGUSAN DEL NORTE 1ST

CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING ROADS, INCLUDING ROW, BDRY. BUKIDNON/AGUSAN DEL NORTE 1ST LD, PACKAGE 2, LAS NIEVES, AGUSAN DEL NORTE 1ST is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱143,749,922.45. Status: Reported complete (DPWH). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱143,749,922.45

Progress

Reported complete (DPWH)

Start Date

August 3, 2017

Target End

June 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.