Buildings and Facilities23IH0127

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), UNIVERSITY OF EASTERN PHILIPPINES, CATARMAN, NORTHERN SAMAR

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), UNIVERSITY OF EASTERN PHILIPPINES, CATARMAN, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱9,883,609.33. Status: Reported complete (DPWH). Contractor on record: ANLE CONST 48373. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱7,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Barangay Lorenzo, Rosario, Northern Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Northern Samar 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,883,609.33

Progress

Reported complete (DPWH)

Start Date

August 17, 2023

Target End

February 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.