Flood Control and Drainage22FB0084

OO2-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TICO-TICO RIVER CONTROL SYSTEM, LEGAZPI CITY

OO2-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF TICO-TICO RIVER CONTROL SYSTEM, LEGAZPI CITY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱38,020,822.00. Status: Past target date (DPWH On-Going). Contractor on record: MAKAPA CORP. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Panal River, Puting Daga Barangay 18 Cabangan Camiri, Brgy. 15 Ilawod East Section, Legazpi City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-22-0000449

₱726,294.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

123 projects · ₱9.7B total · 5 flags

Other projects by this contractor

No sat.

OO2-PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION/REHABILITATION OF NASISI RIVER FLOOD MITIGATION STRUCTURE(BRGY. CAVASI AND BRGY. TOMOL

Region V, Region V

2022₱192.9M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS:CONST./IMPV'T. OF CADAC-AN RIVER FLOOD CONTROL SYSTEM,JUBAN, SORSOGON

Region V, Region V

2018₱185.2M
Reported complete (DPWH)

Construction/Improvement/Rehabilitation of Cadac-an River Flood Mitigation Structure, Sta. 12+260 - Sta. 12+308 Right Side, Sta. 11+792 - Sta. 12+848 Left Side, Juban, Sorsogon

JUBAN (SORSOGON), SORSOGON, Region V

2022₱174.7M
Reported complete (DPWH)

Construction/Improvement/Rehabilitation of Cadac-an River Flood Mitigation Structure, Sta. 23+752.00 - Sta. 24+575.57 Left Side, Sta. 23+806.50 - Sta. 24+357.50 Right Side, Irosin, Sorsogon

IROSIN (SORSOGON), SORSOGON, Region V

2022₱174.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NABONTON RIVER, LIGAO CITY, ALBAY

Region V, Region V

2025₱173.6M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS:CONST.OF FLOOD MITIGATION STRUCTURES ALONG SAN AGUSTIN RIVER,LIBON AL

Region V, Region V

2018₱171.0M
Reported complete (DPWH)
View all 123 projects →

4. Implementation

Contract Amount

₱38,020,822.00

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2022

Target End

August 8, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.