Roads18H00041

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS, CEBU NORTH HAGNAYA WHARF ROAD INCLUDING ROW, K0024+795-K0025+374, K0025+413-K0025+928, K0028+090-K0029+080 AND K0031+963-K0

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS, CEBU NORTH HAGNAYA WHARF ROAD INCLUDING ROW, K0024+795-K0025+374, K0025+413-K0025+928, K0028+090-K0029+080 AND K0031+963-K0 is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱100,441,570.51. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱100,441,570.51

Progress

Reported complete (DPWH)

Start Date

June 11, 2018

Target End

November 22, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.