GAA 2023 OO-223J00221

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL AT SIBUGUEY RIVER ALONG IMELDA-BAYOG-KUMALARANG-LAPUYAN-MARGOSATUBIG ROAD, BARANGAY PARADISE, DIPLAHAN, ZAMBOANGA SIB

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL AT SIBUGUEY RIVER ALONG IMELDA-BAYOG-KUMALARANG-LAPUYAN-MARGOSATUBIG ROAD, BARANGAY PARADISE, DIPLAHAN, ZAMBOANGA SIB is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱48,249,758.96. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,028 projects · ₱22.5B total · 0 flags

4. Implementation

Contract Amount

₱48,249,758.96

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 21, 2023

Target End

February 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.